This page will chart the time line of events.
Jun 04 - Viewed property
Jul 04 - Sealed bid successful
Jul 02/04 - Request for change of use submitted
Aug 13/04 - Moved in
Sept 27/04 - Change of use approved
Oct 04 - Roof removed - Main roof completed 01/02/05, Annex started 21/02/05,Annex completed 21/04/05
Nov 04 - Architect engaged.
24/12/04 - Submitted Building Warrant to NAC for approval.
28/02/05 - Planning Request for porch and sunroom submitted.
02/05/05 - Front elevation being raked out
16/05/05 - Building Warrant approved
16/05/05 - Planning permission granted for porch and sun room
18/06/05 - New Windows fitted
27/06/05 - Construction on Kitchen, utility, porch begins.
08/07/05 - Family/Lounge timber fame completed.
14/07/05 - Kitchen floor, timber frame and masterbed floor in place.
28/08/05 - First fix wiring for downstairs complete. Including networking system.
01/09/05 - Porch nearing completion.
11/09/05 - Gas / Water trenches dug.
30/09/05 - Gas / Water reconnected
05/10/05 - External oak doors installed
15/10/05 - Started upstairs changes - doorways, staircase etc
20/10/05 - Staircase in. Masterbedroom insulated. Ensuite timber framed. New bedroom doorways built.
26/10/05 - Masterbedroom plaster boarded, underfloor heating installed.
12/12/05 - Kitchen UFH installed, and walls insulated.
21/12/05 - Back stairs removed allowing sunroom to begin.
09/01/06 - Concrete stop scree†laid in kitchen, porch and utility room.
28/01/06 - Kitchen walls, electrics, lights in - but concrete floor not dry yet for tiling !.
28/01/06 - Family room insulated and plaster boarded.
25/03/06 - Kitchen 90% complete
08/05/06 - Exterior pointing complete
13/05/06 - Upstairs new Central Heating plumbing in.
22/05/06 - French doors into sunroom begin to take shape
26/05/06 - French doors in. Final structural demolition complete !
05/06/06 - Sunroom starts to take shape.
18/06/06 - Sunroom water tight.
24/06/06 - Sunroom concrete floor goes in.
04/07/06 - Plasterboard the family and lounge.
04/080/07 - Master bedroom plastered
08/08/06 - Porch Plastered
09/08/06 - Gerry +Team finished all the construction work.
10/08/06 - Family room / lounge plastered.
14/08/06 - First fix for new boiler.
Sept 06 - Sunroom/util wired and plasterboarded.
Sep 06 - Painting and decorating family/lounge
07/10/06 - UFH switched on.
14/10/06 - Oak floors laid on the ground floor.
20/10/06 - Stair case and banister completed.
19/11/06 - Downstairs decoration completed.
25/11/06 - Moved downstairs - space at last !.
02/12/06 - Sunroom plastered.
03/02/07 - Sunroom decoration complete.
17/03/07 - Upstairs bedroom demolition complete.
18/03/07 - Upstairs stud walls completed - final room layouts now in place.
Jun 07 - Garden gets a make over - Part 1
Aug 07 - Master bathroom is ripped out
Nov 07 - Study is ripped out, including the window !
May 08 - Building Warrant approved. Remaining restoration is now decoration!
Aug 08 - Hall and stairs plastered
Aug 08 - Kathryns bedroom is completed
Oct 08 - Final room is plastered !!
Oct 08 - Rachels rooms is taking shape
Nov 08 - Rachels room complete
Dec 08 - Downstairs WC is decorated...
Feb 09 - Hallway painted and decorated. Just skirtings left !
April 09 - Oak window cills completed
May 09 - Tackle the garden fence again !
Jun 09 - Hedge removed, and new panel fence installed.
Oct 09 - Oak skirtings and door frames installed on the ground floor
Feb 10 - Back garden clearance
Aug 10 - Back garden patio slabs are laid
Sept 10 - Work on the front boundary walls begins
Nov 10 - Front boundary walls complete (and front sandstone slabs installed)
Nov 10 - Back garden completed !